PRECINCT 3 ONLY
|
Project ID |
Project Name |
From – To Limits |
Project Description / Cost in $ Million |
Construction Starts |
|
703 |
Falcon Landing Boulevard |
Greenbusch Road – Katy Gaston Road |
New location 4-lane curb and gutter boulevard with storm sewer. ($6.0 Total / $3.5 FBC) |
Developer Timeline |
|
719 |
Burney Road |
West Airport Boulevard – Old Richmond Road |
Rehabilitate existing 2-lane rural roadway and add shoulders. ($2.25 FBC) |
Est. Fall 2008 |
|
732 |
Greenbusch Road |
Falcon Landing Boulevard – Katy Flewellen |
Reconstruct to 4-lane curb and gutter with storm sewer. ($11.25 FBC) |
Est. Summer 2008 |
|
733 |
Katy Gaston Road |
Cinco Ranch Boulevard – FM 1093 |
Reconstruct to 4-lane roadway. ($8.75 FBC) |
Est. Spring 2008 |
|
734 |
Katy Flewellen Road |
Pin Oak Road – Katy Gaston Road |
Construct 4-lane curb and gutter with storm sewer. ($7.5 FBC) |
Est. Spring 2008 |
|
735 |
Mason Road |
FM 359 – SH 99 |
Construct 4-lane with storm sewer; partial new location with Skinner Lane ($9.2 Total / $6.1 FBC) |
Developer Timeline |
|
735A |
Mason Road Bridge |
At Oyster Creek |
|
Developer Timeline |
|
739 |
Beechnut Road |
Fort Bend ISD – Harlem Road |
New location 4-lane w/ storm sewer. ($1.5 FBC) |
TBD |
|
741 |
West Bellfort Road |
Harlem Road – SH 99 |
New location 4-lane roadway. ($2.35 FBC) |
Developer Timeline |
|
745 |
Florence Road |
Eldridge Road – Burney Road |
Purchase ROW, study outfall improvements, improve ditches, and add shoulders. ($1.5 FBC) |
Est. Fall 2008 |
|
748 |
FM 1093 |
SH 99 – FM 1463 |
Purchase Metro ROW for the expansion of FM 1093 to 4 lanes |
Depends on Toll Feasibility |
|
720 |
Dulles Ave |
Ave. E – US 90A |
Construct 6-lane concrete. Improve capacity at intersections from SH 6 to Ave. E. ($7.7 Total / $4.3 FBC / $0.4 Sugar Land / $2.5 TxDOT) |
Determined by Sugar Land |
|
762 |
Kingsland Boulevard (City of Katy) |
Medical Center Drive – Willow Fork Road |
New location 4-lane curb and gutter boulevard with storm sewer. ($1.0 Total / $0.5 FBC) |
Determined by Katy |
PRECINCT 3 (SHARED WITH PRECINCT 4)
|
Project ID |
Project Name |
From – To Limits |
Project Description |
Construction Starts |
|
725 |
Harlem Road |
US 90A – Plantation Drive |
Reconstruct to 4-lane asphalt roadway. ($5.5 FBC) |
Est. Fall 2008 |
|
726 |
Harlem Road |
Plantation Drive – SH 99 |
Reconstruct to 4-lane asphalt roadway. ($5.5 FBC) |
TDCJ Timeline |
|
727 |
Harlem Road |
SH 99 – Beechnut Street |
Reconstruct to 4-lane asphalt roadway. ($5.2 FBC) |
Est. Fall 2008 |
|
730 |
Old Richmond Road |
SH 6 – Gaines Road |
Purchase ROW, rehabilitate existing pavement, and add shoulders. ($1.75 FBC) |
TBD |
|
731 |
West Bellfort Road |
Martinez Street – FM 1464 |
New location 4-lane open ditch roadway. ($5.5 FBC) |
TBD |